Monolithic Concrete Slab

Monolithic concrete slab is the most cost effective method for constructing cement floors or concrete garage floor. When pouring concrete slab, if done simultaneously with the footing as depicted by detail 14 below, the term commonly used is Monolithic slab. Due to time saved in labor, this method of constructing cement slab is the most preferred method.

Whether you're doing diy concrete slab or you're working with a contractor, you will still save a lot of money and time with monolithic slab.

Monolithic concrete slab, Pouring a concrete slab, Concrete garage floor, Cement slab, Cement floors Details 12 and 14 are similar that either one can be used for cement floors for houses or concrete garage floor.

Detail 12 requires the footings and foundations to be poured separately prior to the slab. In reality, there will be 3 different pours.

Depending on the complexity of the layout, footing can take 1 to 2 days to form and pour. For foundations it may take up to 5 days depending on the complexity of the layout and the experience of the crew.

If foundation forms are rented, there will be extra day or two to strip the forms, clean them and return. These will result in 7 work days minimum. Additionally, if concrete pumping is required, there will be 3 different trips required @$200+/- per trip, minimum $600+/- Monolithic concrete slab, Pouring a concrete slab, Concrete garage floor, Cement slab, Cement floors By contrast, the monolithic pour will take 2 days max to form and pour all the slabs, footings, and foundations. This will cut the work by 5 days.

For 3 laborers at $10 per hour, the extra 5 days will cost $1,200. Adding the form rental, which can be $600+ depending on size of the project, plus extra two trips of concrete pump - the additional cost can be well above $2,000.

The biggest disadvantage of monolithic pour is it requires a lot more concrete. For 20 ft x 20 ft garage, it will require extra 1 to 2 cubic yards of concrete at $70/cy for additional $140.00. Since the cost of concrete in the US varies widely, this amount of concrete waste can be as much as double or more depending on where you are.

Back to Monolithic concrete slab

more on slab construction Pouring Concrete Slab

From monolithic concrete slab to all-concrete-cement.com

Questions or Comments

We welcome your Questions and/or Comments

[ ? ]

Upload 1-4 Pictures or Graphics (optional)[ ? ]

 

Click here to upload more images (optional)

Author Information (optional)

To receive credit as the author, enter your information below.

(first or full name)

(e.g., City, State, Country)

Submit Your Contribution

  •  submission guidelines.


(You can preview and edit on the next page)

Other Visitors' Questions

Click below to see responses to other visitors' questions...

Uneven Floor Slab, Flawed Construction? 
Question: My wife and I purchased a condo in 2012. The den floor which is concrete on grade (no basement) is very uneven. We have had a concrete expert …

Are there soil requirements for substrate of monolithic 
Question: We have a monolithic slab that cracked and there is displacement on one portion of 1 inch. We had a soil engineer check the substrate and …

monolithic conrete slab cross section 
Question: 12 by 13 feet of slab, i want to know the main bars and transversal bar? Answer: Hi Johnson, thanks for visiting all-concrete-cement.com …

Block wall on existing slab 
Question: I have an old existing slab that is 11 x 16 ft 4" thick. At one time I had a metal shed on it but it got rusty and we tore it down. I want …

Click here to write your own.